Magor Road, Newport, Wales
Section 278 scheme to build a new bellmouth into industrial estate incorporating road widening, pedestrian islands, cycleway, footpaths and bus-stops. This scheme had the additional complication of spanning 2 local
Duration: 16 Weeks
Valuation: £349,000
View Project
Avocet Phase 3, Ferry Lane, Dagenham, London
Section 278 scheme to build 2 entrances into new industrial estate which involved the construction of an 80 tonne culvert in an active waterway. Local Authority: Havering Council
Duration: 8 Weeks
Valuation: £205,000
View Project
Boatman’s House, Canary Wharf
What once was a pedestrian area is now a reinforced concrete foundation for a temporary display home:
Duration: 2 Weeks
Valuation: £48,000
View Project
Weston House, Sawbridgeworth
Weston House A new carpark and drainage for the purpose of a new office building:
Duration: 8 weeks
Valuation: £153,500
View Project
City Quay, Thomas More Street, London, E1
This project was in a very prestigious apartment block next to St Catherines dock. The project was to strip off the access road and footpaths to expose the concrete roof
Duration: 20 Weeks
Valuation: £252,000
View Project
Colonial Way, Watford, Herts
Section 50 to construct new manhole in the middle of the carriageway which had to be completed over a weekend as the road had to re-open on the Monday. Local
Duration: 14 Weeks
Valuation: ££216,000
View Project
Epping Forest – City of London Corporation
We have conducted works for the Corporation at the majority of their sites in and around Epping Forest. This includes car park rejuvenation and repairs, natural stone tracks and paths,
Duration: 30+ Projects between 1-4 weeks
Valuation: £-
View Project
Fleets Lane, Poole, Dorset
Scheme to build a new entrance into industrial estate and re-surface the carriageway in front of the site.. Section 50 to construct new manhole in the middle of the carriageway
Duration: 8 Weeks
Valuation: ££312,000
View Project
Great Baddow School, Chelmsford
This project involved the construction of a car park for 125 vehicles. Most projects we work on in schools is done during the holidays but this had to be completed
Duration: 4 Weeks
Valuation: ££185,000
View Project
Launton Road, Bicester, Oxfordshire
Section 278 scheme to build bellmouth into industrial estate incorporating, pedestrian islands, cycleway, footpaths and 10 new streetlamps. Section 50 to connect foul and storm water to local sewer. Local
Duration: 12 Weeks
Valuation: £253,000
View Project
Newham Hospital, Glen Road, London
The project was to build a car park for 100 vehicles on waste land next to the new Neurological block. Working within NHS land brings many challenges especially around Health
Duration: 10 Weeks
Valuation: £178,000
View Project
Pinewood Studios
This project involved the planning off and resurfacing of the famous 007 Way that ran through the studios where James Bond was made in the 80’s. The work had to
Duration: 3 Weeks
Valuation: ££51,000
View Project
River Way, Harlow, Essex
Section 278 scheme to build 3 new bellmouths into industrial estate incorporating resurfacing the carriageway in HRA/chip. Project incorporated the installation of 10 new streetlamps. Local Authority: Essex Highways
Duration: 16 Weeks
Valuation: £215,000
View Project
Surrey Downs – City of London Corporation
We have conducted works for the Corporation at the majority of their sites across the Surrey Downs. This includes car park rejuvenation and repairs, natural stone tracks and paths, barriers
Duration: 20+ Projects between 1-4 weeks
Valuation: £-
View Project
Weston House, Maltings, Sawbridgeworth, Hertfordshire
This project was challenging in that we needed to construct a very large attenuation under the new car park that could bear 80 tonne. Once the tank was built all
Duration: 10 Weeks
Valuation: £153,000
View Project
White Lodge, Norwich, Norfolk
Section 50 to install a new foul water connection at 6m below ground involved the use of a robotic excavator and using our High risk confined space trained operatives. Local
Duration: 3 Weeks
Valuation: ££65,000
View Project
Woodside Trading Estate, Epping, Essex
Section 278 works to construct 2 bellmouths to the trading estate. The project involved re-surfacing the access road within the estate with multiple sleeping policemen. Local Authority: Essex Highways
Duration: 6 Weeks
Valuation: £179,000